Other works in progress

Other minor capital projects may also be underway. Some projects may take a bit longer than anticipated to complete due to extended periods of rain, or contractors availability.

 You can also follow the progress of council's major regional projects.


Search Minor works

32 results found

Aroona, Beerburrum Street - Signalisation of pedestrian crossing

Aroona

Works will begin soon on the upgrade of the pedestrian crossing at Beerburrum Street, Aroona which will provide a safe crossing to Ridgehaven Park.

Start Date
Duration12 weeks

Works will begin soon on the upgrade of the pedestrian crossing at Beerburrum Street, Aroona which will provide a safe crossing to Ridgehaven Park.

The upgraded pedestrian crossing will include traffic/pedestrian lights and more road lighting.

Work is scheduled to start late May 2023. Residents adjacent to the works will be updated closer to commencement.

Construction is expected to be completed within three months, weather and site conditions permitting.

Your patience during construction is appreciated.

Project News - K3739 - Div 3 - Signalisation Pedestrian Crossing Beerburrum St Aroona

Bli Bli, Camp Flat Road - Stage4 upgrade

Bli Bli

Sunshine Coast Council is committed to the ongoing improvement of local road networks within the region. Council has received partial funding from the Department of Transport and Main Roads (TMR) Transport Infrastructure Development Scheme (TIDS) to continue the upgrade along Camp Flat Road, Bli Bli.

Start Date
DurationLate 2023 and early 2024

Stage 4 will resume from the previous section of Camp Flat Road completed in 2021 and will also include the Whitecross Road intersection.

An experienced fauna spotter-catcher will be in attendance to manage and supervise all terrestrial fauna management activities prior to and during tree removal works.

Early works will include the construction of a retaining wall on Camp Flat and Whitecross roads intersection, as well Energex and NBN relocations.

More details will be provided to the community prior to these early works commencing.

The main construction is expected to commence between late 2023 and early 2024. Further information will be provided prior to this main construction phase.

Tree clearing works for a new Energex corridor is planned to commence 12 June 2023 with early works expected to start in July 2023, weather and site conditions permitting. Project news - K2723 - Div 9 - Stage 4 upgrade Camp Flat Rd Bli Bli (PDF, 1MB).

The construction of a masonry block retaining wall on the north-east corner of Camp Flat and Whitecross roads is planned to commence Monday 4 September 2023. Project news - K2723 - Div 9 - Stage 4 upgrade Camp Flat Rd Bli Bli (PDF, 317.65KB).

Bli-Bli, Petrie Creek Catchment - Waterway Improvements

Bli Bli

A design has been developed for the naturalisation of a section of waterway within Princess Drive Park, Bli Bli.

Start Date
DurationOctober 2024

The waterway comprises a low-flow concrete drainage channel within a grassed, open swale area. Please refer to figure 1 overleaf.

The works aim to naturalise the waterway corridor. This will establish a high value public open space which integrates with the existing environmental, social and cultural values of the area.

Project News - H4900 - Div 9 - Waterway Rehab - Petrie Ck Catchment Bli Bli

Bokarina, Meridian Street and Nicklin Way-Pathway Improvements

Bokarina

Sunshine Coast Council is committed to improving and maintaining pathway networks across our region. In partnership with the Queensland Government, Council will be widening footpaths around Kawana Waters State College.

Start Date
Duration2 weeks, weather permitting

A 300m long section of existing 1.2m footpath will be widened to 2m to allow for the growing volume of pathway users.

The upgraded path will extend from Meridan Street at Sportsmans Parade to 382 Nicklin Way (Beaumont Tiles), Bokarina.

See attached document for location of works.

Project News - K6537 - Div 3 - Pathway Improvements Nicklin Way Meridan St Kawana Waters

Buderim Lions Park - New Public Amenity Block

Buderim

Sunshine Coast Council is committed to maintaining and improving our parks and recreational spaces across the region.

Start Date
Duration7 weeks

As part of these ongoing improvements, we are replacing the public amenity block at the Buderim Lions Park with a new disability compliant amenity block.

The new public amenity block will consist of one disability compliant and two ambulant toilets to service its patrons and wider community.

Project News - H2095 - Div 6 - Buderim Lions Park Public Amenity Block

Caloundra, Bingera Terrace - Stormwater Pit Upgrade

Caloundra

Sunshine Coast Council is committed to maintaining our infrastructure across the region. As part of this year’s stormwater renewal program, council is replacing three stormwater pits on Bingera Terrace, Caloundra.

Start Date
Duration2 weeks

Work is scheduled to start the week beginning Monday 4 December 2023. Construction is expected to be completed within two weeks, weather and site conditions permitting.

Work will occur between 7am and 5pm on weekdays.

Project News - K4387 - Div 2 - SW Pit Upgrade Bingera Tce Caloundra

Caloundra, Tripcony Lane - Maloja Pontoon Renewal

Caloundra

Sunshine Coast Council has replaced the well-used Maloja Pontoon at Tripcony Lane, Caloundra with an even more accessible jetty for all members of our community. The new 12 x 4 metre pontoon features a much more modern design, including a durable concrete deck that is perfect for fishing and boating.

Start Date
DurationComplete

A modified design to the new pontoon provides a gentler sloping gangway that improves accessibility for all users, especially at low tide.

Council invested $220,000 in partnership with the Queensland government, which provided assistance through an $80,000 Fishing Infrastructure Grant, funded by the Commonwealth Government.

Thank you for your patience during the reconstruction works. We’re sure this new Maloja Pontoon will continue to be a popular spot for our community, boaties, water users and fishing enthusiasts well into the future.

Project News - Div 2 - K2441 - Maloja Poontoon Renewal - Tripcony Lane - Caloundra

Coolum Beach, Jack Morgan Park-New Public Amenities

Coolum Beach

Sunshine Coast Council is committed to maintaining and improving our parks and recreational spaces across our region.

Start Date
DurationApprox. 7 weeks, shut down 22 Dec 2023 - 08 Jan 2024

As part of these ongoing improvements, a new public amenity block will be installed at Jack Morgan Park in Coolum Beach.

The new public amenities will consist of one disability compliant toilet and four ambulant toilets.

Project News - H7141 - Div 9 - New Public Amenities Jack Morgan Park Coolum Beach

Currimundi, Buderim Street - Pathway Improvements

Currimundi

Sunshine Coast Council is committed to improving and maintaining pathway networks across our region. In partnership with the Queensland Government, Council will be widening footpaths around Currimundi State School and Currimundi Special School.

Start Date
DurationThe Western section on the South side of Buderim Street will be constructed from 11-21 December 2023, weather permitting. The Eastern section (towards the beach) will be constructed from 8-19 January 2024, weather permitting.

The existing 1.2m wide footpath will be widened to 2-2.5 metres to allow for the growing volume of pathway users.

Works will be undertaken during the school holidays in two sections:

  • Eastern section – 2m wide path constructed from the main school entrance to the coastal pathway.
  • Western section – 2 to 2.5m wide path constructed from the signalised crossing at the school to the Currimundi Hotel.

See attached Project News for location of works.

Project News - K4382 - Div 3 - Pathway Improvements Buderim St Currimundi

Doonan Creek Environmental Reserve - Walking Trail Install

Doonan

Sunshine Coast Council will soon be undertaking the construction of a walking trail as part of the Doonan Creek Environmental Reserve Landscape Plan.

Start Date
Duration12 weeks

Stage 1 works include the renewal and installation of a gravel trail, pedestrian pathway and boardwalk, totalling approximately 590 metres.

Works are scheduled to start late August and be completed by October 2023, weather and site conditions permitting.

Project News - K3236 - Div 9 - Walking Trail Doonan Creek Environmental Reserve

Dicky Beach, Coochin Street - New Footpath

Dicky Beach

Sunshine Coast Council will be constructing a new footpath along the North side of Coochin Street, Dicky Beach.

Start Date
Duration2 weeks

The new path will connect the existing footpath on Cooroy Street with the coastal pathway at Dicky Beach Surf Club.

The design has been carefully reviewed to minimise vegetation clearing wherever possible, however approximately six trees will be removed to facilitate the new pathway.

To offset the removal, new trees/landscaping will be planted along the new pathway following the completion of the works.

Project News - K6248 - Div 2 - New Pathway Coochin St Dicky Beach

Eudlo Stage 2, Perrins Road-Gravel Road Upgrade

Eudlo

Work will soon commence on the unsealed section of Perrins Rd approximately 1km from the intersection of Logwoods Rd. Works will include widening, sealing and the construction of retaining structures.

Start Date
Duration12 weeks

Unfortunately, some trees will need to be removed to construct the roadworks and maintain safe sight lines. A fauna spotter-catcher will be on-site to monitor clearing. All tree clearing will be offset by planting at one of Council’s environmental reserves at a ratio of 4:1.

Works are currently scheduled to start Monday, 28 August 2023 and be completed by Friday, 24 November. Weather and site conditions permitting.

Project News - Div 5 - H2043 - Perrins Rd Eudlo - Stage 2 Gravel Road Upgrade

Golden Beach, Beryl Street - Stormwater Pit Upgrade

Golden Beach

Sunshine Coast Council is committed to maintaining our infrastructure across the region.

Start Date
Duration1 week

As part of this year’s Stormwater Renewal Program, council is replacing one stormwater pit on Beryl Street, Golden Beach.

Project News - K4387 - Div 2 - SW Pit Upgrades Beryl St Golden Beach

Golden Beach, Haig Street - Stormwater Pit Upgrade

Golden Beach

Sunshine Coast Council is committed to maintaining our infrastructure across the region.

Start Date
Duration2 week

As part of this year’s Stormwater Renewal Program, council is replacing three stormwater pits on Haig Street, Golden Beach.

Project News - K4387 - Div 2 - SW Pit Upgrades Haig St Golden Beach

Golden Beach, Monash Street - Stormwater Pit Upgrade

Golden Beach

Sunshine Coast Council is committed to maintaining our infrastructure across the region. As part of this year’s Stormwater Renewal Program, council is replacing two stormwater pits on Monash Street, Golden Beach.

Start Date
Duration2 weeks, weather and site conditions permitting.

Work is scheduled to start the week beginning Monday 11 December 2023. Construction is expected to be completed within two weeks, weather and site conditions permitting.

Work will occur between 7am and 5pm on weekdays.

Please refer to attached Project.

Project News - K4387 - Div 2 - SW Pit Upgrades Monash St Golden Beach

Kawana Aquatic Centre - Upgrade

Bokarina

Major upgrades are underway for Kawana Aquatic Centre and the facility remains fully operational during this time.

Start Date
DurationOngoing

Major upgrades are underway for Kawana Aquatic Centre and the facility remains fully operational during this time.

The first of three construction stages (Stage 1A and 1B) involve a new indoor program pool, along with improved structures, plant, operating equipment, and demolition of the existing indoor pool.

Council advertised the tender for construction of Stage 2 in October 2023.

Future works include a new entry building, public amenities and changerooms, a refurbished kiosk, and improved car parking.

Construction of Stage 1 is expected to be completed in early 2024, weather and site conditions permitting.

Project News Update Oct 2023 - Kawana Aquatic Centre

Kings Beach, Dingle Avenue - Stormwater Pit Upgrade

Kings Beach

Sunshine Coast Council is committed to maintaining our infrastructure across the region. As part of this year’s stormwater renewal program, council is replacing a stormwater pit on Dingle Avenue, Kings Beach.

Start Date
Duration1 week

Work is scheduled to start the week beginning Monday 27 November 2023. Construction is expected to be completed within one week, weather and site conditions permitting.

Work will occur between 7am and 5pm on weekdays.

Project News - K4387 - Div 2 - SW Pit Upgrade Dingle Ave Kings Beach

Kings Beach, Ormonde Terrace - Stormwater Pit Upgrade

Kings Beach

Sunshine Coast Council is committed to maintaining our infrastructure across the region. As part of this year’s Stormwater Renewal Program, council is replacing two stormwater pits on Ormonde Terrace, Kings Beach.

Start Date
Duration2 weeks, weather and site conditions permitting

Work is scheduled to start the week beginning Monday 11 December 2023. Construction is expected to be completed within two weeks, weather and site conditions permitting.

Work will occur between 7am and 5pm on weekdays.

Please refer to attached Project News

Project News - K4387 - Div 2 - SW Pit Upgrades Ormonde Tce Kings Beach

Landsborough, Forestdale Road - Stormwater Pit Upgrade

Landsborough

Sunshine Coast Council is committed to maintaining our infrastructure across the region. As part of this year’s Stormwater Renewal Program, council is replacing one stormwater pit on Forestdale Road, Landsborough.

Start Date
Duration1 week, weather and site conditions permitting.

Work is scheduled to start the week beginning Monday 18 December 2023. Construction is expected to be completed within one week, weather and site conditions permitting.

Work will occur between 7am and 5pm on weekdays.

Please refer to the attached Project News.

Project News - K4387 - Div 1 - SW Pit Upgrades Forestdale Road Landsborough

Maroochydore, Cooninda Crescent - New Pathway

Maroochydore

Sunshine Coast Council will be constructing a new footpath along the eastern side of Cooinda Crescent, Maroochydore.

Start Date
Duration2 weeks

The new footpath will span from the Homemaker Centre carpark 160 metres along Cooinda Crescent.

This is part of a staged project to connect the Homemaker Centre to the existing footpath at Boongala Terrace.

Project News - K5478 - Div 8 - New Pathway Cooinda Cr Maroochydore