About the Maple Street project
Learn about the vision, design features and benefits of the Maple Street upgrade.
The project is a direct outcome of the Maple Street Streetscape Concept Plan and reflects what the community told us mattered most for Maleny’s main street.
The upgraded streetscape incorporates the area of Maple Street between Myrtle and Teak Streets. It will create a more welcoming and accessible main street through:
- new raised pedestrian crossings with improved lighting
- more shade trees and garden areas
- extended kerbs and footpath upgrades in key areas
- new seating and places for people to meet and gather
- wayfinding signage
- a heritage trail and cultural interpretation elements
- safer and compliant car parking.
Landscaping is a major focus of the upgrade, with more shade trees and gardens to support comfort, sustainability and a greener streetscape. This includes more than 580 new trees and shrubs, along with new seating and community gathering spaces.
The project received additional funding through the Australian Government - Local Roads and Community Infrastructure grant program. This enabled us to increase the project scope to include upgrades to some key sections of footpaths along the street.
What community engagement was conducted as part of the project?
Our community played a strong role in shaping the final design, with extensive community engagement between 2022 and 2023.
More than 66 per cent of participants support the streetscape improvements, with 67 percent agreeing the design reflects the shared values and vision for Maple Street.
The final design uniquely reflects the character and history of the township.
To learn about the previous community engagement process, please visit our Have your Say website.
Project timeline
2001-2010 - Initial community engagement undertaken for Maleny Streetscape Concept Plan (2005)
Early 2022 - Project planning complete
July - August 2022 - Phase 1 - Community engagement ‘Review & refresh’
To gain feedback on the Maleny Streetscape Diagram.
July – August 2023 - Phase 2 - Community engagement ‘Testing the plan’
To gain feedback on the refined Concept Plan.
December 2022 – April 2023 - Detailed design
May - July 2024 - Tender documentation
October 2025 - Conditional approval received from Department of Transport and Main Roads (DTMR)
December 2025 - May 2026 - Contractor procurement
June 2026 - Contractor site office establishment - Approval to proceed application to Department of Transport and Main Roads (DTMR)
July 2026 to March 2027 (weather permitting) - Construction - We’ve engaged local company Disc Landscapes to deliver the works.
- Start: Week commencing Monday 6 July 2026
- Finish: March 2027 (weather and site conditions permitting)
Works will be done in stages across two zones to reduce impacts:
- Zone 1: Teak Street to Fig Street
- Zone 2: Fig Street to Myrtle Street
Sneak peek: Maple Street's new look
Scroll right to see the before and after images (artist impressions) of the streetscape upgrade.