Other works in progress
Other minor capital projects may also be underway. Some projects may take a bit longer than anticipated to complete due to extended periods of rain, or contractors availability.
You can also follow the progress of council's major regional projects.
20 results found
Aroona, Beerburrum Street - Signalisation of pedestrian crossing
Aroona
Works will begin soon on the upgrade of the pedestrian crossing at Beerburrum Street, Aroona which will provide a safe crossing to Ridgehaven Park.
Start Date | |
Duration | 12 weeks |
Works will begin soon on the upgrade of the pedestrian crossing at Beerburrum Street, Aroona which will provide a safe crossing to Ridgehaven Park.
The upgraded pedestrian crossing will include traffic/pedestrian lights and more road lighting.
Work is scheduled to start late May 2023. Residents adjacent to the works will be updated closer to commencement.
Construction is expected to be completed within three months, weather and site conditions permitting.
Your patience during construction is appreciated.
Project News - K3739 - Div 3 - Signalisation Pedestrian Crossing Beerburrum St Aroona
Beerwah, Emma Place - New Footpath
Beerwah
Sunshine Coast Council will be improving connectivity with a new footpath along the worn track at Caralan Way Park, Beerwah.
Start Date | |
Duration | 1 week |
The new footpath will span approximately 180 metres from Emma Place along the existing dirt pathway alignment.
No trees will be removed or impacted for this new footpath.
Project News - K5466 - Div 1 - New Pathway Emma Place into Caralan Way Park Beerwah
Bli Bli, Camp Flat Road - Stage 4 road upgrade
Bli Bli
Sunshine Coast Council is committed to the ongoing improvement of local road networks within the region. Council has received partial funding from the Department of Transport and Main Roads (TMR) Transport Infrastructure Development Scheme (TIDS) to continue the upgrade along Camp Flat Road, Bli Bli.
Start Date | |
Duration | Late 2023 and early 2024 |
Stage 4 will resume from the previous section of Camp Flat Road completed in 2021 and will also include the Whitecross Road intersection.
An experienced fauna spotter-catcher will be in attendance to manage and supervise all terrestrial fauna management activities prior to and during tree removal works.
Early works will include the construction of a retaining wall on Camp Flat and Whitecross roads intersection, as well Energex and NBN relocations.
More details will be provided to the community prior to these early works commencing.
The main construction is expected to commence between late 2023 and early 2024. Further information will be provided prior to this main construction phase.
Tree clearing works for a new Energex corridor is planned to commence 12 June 2023 with early works expected to start in July 2023, weather and site conditions permitting. Project news - K2723 - Div 9 - Stage 4 upgrade Camp Flat Rd Bli Bli (PDF, 1MB).
The construction of a masonry block retaining wall on the north-east corner of Camp Flat and Whitecross roads is planned to commence Monday 4 September 2023. Project news - K2723 - Div 9 - Stage 4 upgrade Camp Flat Rd Bli Bli (PDF, 317.65KB).
Bli Bli, Hagen Place - Stormwater Pit Upgrades
Bli Bli
Sunshine Coast Council is committed to maintaining our infrastructure across the region.
Start Date | |
Duration | 1 week |
As part of this year’s Stormwater Renewal Program, council is replacing two stormwater pits on Hagen Place, Bli Bli.
Project News - K4387 - Div 9 - SW Pit Upgrade Hagen Pl Bli Bli
Bokarina, Kawana Aquatic Centre - Upgrade
Bokarina
Major upgrades are underway for Kawana Aquatic Centre and the facility remains fully operational during this time.
Start Date | |
Duration | 35 weeks |
The first of three construction stages (Stage 1A and 1B) involve a new 20-metre indoor pool, along with improved structures, plant, operating equipment, and demolition of the existing indoor pool.
Timing for Stage 2 and Stage 3 is still to be determined.
Future works include a new entry building, children’s water play areas, public amenities, a refurbished kiosk, and improved car parking.
Construction is expected to be completed by November 2023, weather and site conditions permitting.
Buderim, Jingellic Drive - New pathway
Buderim
Council is committed to increasing and maintaining pathway networks across our region. Construction will begin soon on a new footpath along the western and northern side of Jingellic Drive, Buderim.
Start Date | |
Duration | 3 weeks |
The path will extend 180m from the roundabout on Karawatha Street to 17 Jingellic Drive.
To allow for a smooth and accessible connection, the path will be widened to two metres. The works have been carefully reviewed to minimise vegetation clearing, however it is necessary to remove five trees. As part of the council’s commitment to sustainability, 10 trees will be planted as offset along the new pathway.
This project is scheduled to start on Monday 4 September 2023 and will be finished within 3 weeks, weather and site conditions permitting.
Project News - K1055 - Div 6 - New Pathway Jingellic Drive Buderim (PDF, 453.08KB).
Caloundra, Caloundra Esplanade - Footpath renewal
Caloundra
Sunshine Coast Council is committed to increasing and maintaining pathway networks across our region.
Start Date | |
Duration | 3 weeks |
Construction will begin soon on renewing and widening the existing footpath to 1.8 metres wide along the Northern side of Caloundra Esplanade from Minchinton Street to Knox Avenue, Caloundra.
A total length of 197 metres of path will be renewed. Ramps to the road will also be renewed.
Project News - H7739 - Div 2 - Pathway Renewal Caloundra Esplanade
Caloundra, Tripcony Lane - Maloja Pontoon Renewal
Caloundra
The pontoon at Tripcony Lane is well-used and enjoyed by all. However, it has reached the end of its life and needs to be replaced. To develop the final design, Sunshine Coast Council rigorously investigated what type of structure would best suit the changing conditions in the Pumicestone Passage.
Start Date | |
Duration | 4 weeks |
To develop the final design, Sunshine Coast Council rigorously investigated what type of structure would best suit the changing conditions in the Pumicestone Passage.
We asked the community what type of structure would best suit their needs via an online survey, conducted a detailed site investigation and a review of what would offer best value for the investment.
From these investigations, Council determined that a pontoon would best meet the needs of the users, with some improvements over the existing structure.
Project News - Div 2 - K2441 - Maloja Poontoon Renewal - Tripcony Lane - Caloundra
Coolum Sports Complex - Intersection Upgrade
Coolum Beach
Sunshine Coast Council is pleased to announce the upgrade to the entrance of the Coolum Sports Complex.
Start Date | |
Duration | 6 weeks, weather and site conditions permitting |
The works will see additional capacity for vehicles exiting the complex and the addition of a slip lane for vehicles exiting northbound. Lighting at the intersection will also be upgraded with additional light poles added for improved visibility at night.
Works also include necessary realignment of utilities to allow construction to start.
Cotton Tree, Fourth Avenue - Stormwater Upgrades
Cotton Tree
Sunshine Coast Council is committed to improving stormwater infrastructure across our region. As part of this year’s Stormwater Renewal Program, council is undertaking construction of multiple new stormwater chambers and associated infrastructure to improve this network.
Start Date | |
Duration | 4 weeks |
The chambers are of significant size, and the methodology chosen is to utilize precast concrete to reduce the impact to the pavement, as well as limit road closure times.
Dewatering and water treatment processes will be in operation, and fenced exclusion zones will be in place for public safety.
Project News - K3791 - Div 4 - SW Upgrades Fourth Ave Cotton Tree
Doonan Creek Environmental Reserve - Walking Trail Install
Doonan
Sunshine Coast Council will soon be undertaking the construction of a walking trail as part of the Doonan Creek Environmental Reserve Landscape Plan.
Start Date | |
Duration | 12 weeks |
Stage 1 works include the renewal and installation of a gravel trail, pedestrian pathway and boardwalk, totalling approximately 590 metres.
Works are scheduled to start late August and be completed by October 2023, weather and site conditions permitting.
Project News - K3236 - Div 9 - Walking Trail Doonan Creek Environmental Reserve
Dicky Beach, Coochin Street - New Footpath
Dicky Beach
Sunshine Coast Council will be constructing a new footpath along the North side of Coochin Street, Dicky Beach.
Start Date | |
Duration | 2 weeks |
The new path will connect the existing footpath on Cooroy Street with the coastal pathway at Dicky Beach Surf Club.
The design has been carefully reviewed to minimise vegetation clearing wherever possible, however approximately six trees will be removed to facilitate the new pathway.
To offset the removal, new trees/landscaping will be planted along the new pathway following the completion of the works.
Project News - K6248 - Div 2 - New Pathway Coochin St Dicky Beach
Eudlo Stage 2, Perrins Road-Gravel Road Upgrade
Eudlo
Work will soon commence on the unsealed section of Perrins Rd approximately 1km from the intersection of Logwoods Rd. Works will include widening, sealing and the construction of retaining structures.
Start Date | |
Duration | 12 weeks |
Unfortunately, some trees will need to be removed to construct the roadworks and maintain safe sight lines. A fauna spotter-catcher will be on-site to monitor clearing. All tree clearing will be offset by planting at one of Council’s environmental reserves at a ratio of 4:1.
Works are currently scheduled to start Monday, 28 August 2023 and be completed by Friday, 24 November. Weather and site conditions permitting.
Project News - Div 5 - H2043 - Perrins Rd Eudlo - Stage 2 Gravel Road Upgrade
Little Mountain, Winchester Road-New footpath and kerb ramps
Little Mountain
Sunshine Coast Council is committed to increasing and maintaining pathway networks across our region. Construction will begin on a new footpath along the western side of Winchester Road, Little Mountain.
Start Date | |
Duration | 2 weeks |
The new 1.8m-wide path will connect the existing footpath from Winchester Road to Woodroffe Street. Kerb ramps are also being installed across Winchester Road to allow for easier crossing and future connectivity.
Works are expected to commence Monday 2 October 2023 and be finished within a week, weather and site conditions permitting.
Project News - P-K1071 - Div 1 - New Pathway Kerbs Winchester Road Little Mountain
Mountain Creek, Glenfields Neighbourhood Park-New Amenity Block
Mountain Creek
Sunshine Coast Council is committed to maintaining and improving our parks and recreational spaces across our region.
Start Date | |
Duration | 8 weeks |
As part of these ongoing improvements, a new public amenity block will be constructed at Glenfields Neighborhood Park, Mountain Creek. The new public amenity block will consist of one disability and one unisex toilet to service its patrons and wider community.
A disability compliant car space and interconnecting pathways will also be constructed on Glenfields Boulevard.
The works have been carefully reviewed to minimise vegetation clearing, however it is necessary to remove one tree. As part of council’s commitment to sustainability, several trees will be planted as offset in the surrounding area of Glenfields Neighbourhood Park.
Project News - K1456 - Div 6 - New Public Amenities - Glenfields Neighbourhood Park Mountain Creek
Mt Coolum, Lumeah Drive - New pathway
Mount Coolum
Sunshine Coast Council will be constructing a new footpath along Lumeah Drive, in Mount Coolum.
Start Date | |
Duration | 2 weeks |
The new footpath will span from the Mount Coolum Golf Club to Suncoast Beach Drive.
Project News - K5475 - Div 8 - New Pathway Lumeah Drive - Mt Coolum
Mount Coolum, Lumeah Drive - Stormwater Pit Upgrade
Mount Coolum
Sunshine Coast Council is committed to maintaining our infrastructure across the region.
Start Date | |
Duration | 2 weeks |
As part of this year’s stormwater renewal program, council is replacing one stormwater pit on Lumeah Drive, Mount Coolum.
Project News - K4387 - Div 8 - SW Pit Upgrade Lumeah Dr Mount Coolum
Nambour, Parson Street - Stormwater pit upgrade
Nambour
As part of this year’s stormwater renewal program, council is replacing two stormwater pits in the easement behind Parsons Street, Nambour.
Start Date | |
Duration |
As part of this year’s stormwater renewal program, council is replacing two stormwater pits in the easement behind Parsons Street, Nambour.
Project News - K4387 - Div 10 - SW Pit Upgrade Parsons St Nambour
Yandina, North Arm Yandina Creek Road Stage 3
Yandina
Sunshine Coast Council maintains more than 2200 kilometres of roads across our region through its road reseal and rehabilitation program to ensure they are safe for all road users.
Start Date | |
Duration | 6 months |
As part of this program, we will start the North Arm Yandina Creek Road Stage 3 gravel road upgrade in September 2023.
The overall project will deliver an upgraded and sealed roadway between the currently sealed section of North Arm Yandina Creek Road and the intersection of North Arm Yandina Creek Rd and Toolborough Road
This project will improve road safety, reduce future maintenance requirements, improve dust suppression for the community who travel along or live close to North Arm Yandina Creek Road.
It will also improve visibility and safety for all road users and make it safer for residents entering and exiting their properties.
Project News - H1251 - Div 9 - Gravel Rd Upgrade Stg 3 North Arm Yandina Ck Rd
Yarooma, Yarooma Park - Playground Renewal
Yaroomba
Sunshine Coast Council will soon be renewing the playground at Yaroomba Park in Yaroomba. The renewal works include demolishing and removing the existing seesaw, two rockers and timber edging, and installing new boulders and softfall mulch. The existing swing will remain.
Start Date | |
Duration | 2 weeks |
Yaroomba playground will be closed for the duration of the works.
All other access to Yaroomba Bushland Park will remain as is throughout construction.
Thank you in advance for your patience while we deliver these works for our community.
Project News - Div 8 - K1202 - Yaroomba Park Playground Renewal - Yaroomba