Schedule of work
  • Last updated:
  • 31 Aug 2021

The schedule of work is subject to weather conditions and can change due to circumstances outside of council's control.

Contractors carry out this work on behalf of council.

Detours may be in place to assist with traffic flow during these times and every attempt will be made to minimise disruptions. Your patience while this important work is carried out is appreciated.

Please slow down and follow traffic directions near all road works, for your safety and that of the people working on the roads.

Day work generally starts at 7 am and finishes at 5 pm.

Suburb    Street Start Date Notifications Duration
Division 1   Various Roads 7 November Maintenance road surface line marking 4 weeks
Division 1
  Gattera Road, Landsborough 17 November Road Spray Seal 2 weeks
Division 1
  Alfs Pinch Road, Beerwah 16 November Road Spray Seal 2 weeks
Division 1
  Commissioners Flat Road, Peachester 16 November Road Spray Seal 2 weeks
Division 3   Albatross Avenue, Aroona 14 November Reseal and Rehabilitation 16 weeks
Division 4   Gull Place Parrearra 21 November Road Spray Seal 2 weeks
Division 4   Lory Place, Parrearra 21 November Road Spray Seal 2 weeks
Division 4   Benalla Street, Echuca Courtand Bakali Court, Warana 21 November Road Spray Seal 2 weeks
Division 5 Reesville Raod, Reesville 15 November Road Spray Seal 2 weeks
Division 5 Rifle Range Road, Palmwoods 18 November Road Spray Seal 2 weeks
Division 5   Whites Road, Landsborough 17 November Road Spray Seal 2 weeks
Division 5   Corks Pocket Road, Reesville 14 November Road Spray Seal 2 weeks
Division 5   Mckees Road, Palmwoods 23 November  Road Spray Seal 2 weeks
Division 5   Aherns Road and Kilcoy Lane 28 November Road Spray Seal 2 weeks
Division 6   Greenhaven Drive 3 November Road Reseal 6 weeks
Division 7   Lakeshore Avenue, Aspen Court, Kalmala Court, Edenvale Court, Bangalow Court, Glenbrae Court, Greenvale Court, Woodlot Court and Woodlands Crescent, Buderim 29 November Road Reseal 2 weeks
Division 8 Alkira Street, Berrima Street, Beelah Street, Minti Street, Ingara Street and Yinni Street, Maroochydore 23 November Road Reseal 2 weeks
Division 10   Crystal Street, Topaz Street and Emerald Court Mapleton 7 November Kerb & Channel 2 weeks
Division 10   Towen Mountain Road, Towen Mountain 23 November Road Spray Seal 2 weeks
Division 10   Angus Crescent, and Jewett Road, Kureelpa 23 November Road Spray Seal 2 weeks
Division 10   Various Roads 1 September Maintenance road surface line marking 12 weeks
Division 10
  Droughtmaster Crescent and Hereford Drive 24 November Road Spray Seal 2 weeks
Division 10
  Shorthorn Crescent and Murray Grey Drive 24 November Road Spray Seal 2 weeks
Division 10
  Kureelpa Falls Road 24 November Road Spray Seal 2 weeks
Division 10
  Creightons Road and Mount Coombes Road 25 November Road Spray Seal 2 weeks
Division 10
  Mount Cooroy Road 28 November Road Spray Seal 2 weeks

Road Spray Seal
 







































Night work occurs between 6 pm and 5 am.

Suburb​

Street 

Start date 

Notifications Duration
Division 1 Various Roads 7 November Maintenance road surface line marking 4 weeks
Division 6 Greenhaven Drive and Pignata Road 3 November Road Reseal 2 weeks
Division 10 Various Roads 1 September Maintenance road surface line marking 12 weeks

















Traffic management

Local residents will be able to access their properties during working hours and traffic management measures will be in place for the safety of pedestrians and motorists.

Vehicle movement in the streets will be restricted when work starts and every attempt to minimise disruptions will be made. 

It is recommended to plan ahead and allow more time for your travel during work periods. 

Your cooperation and patience is appreciated while work is underway.

More information

If you would like more information on the program please contact council's customer service centre