Schedule of work
  • Last updated:
  • 31 Aug 2021

The schedule of work is subject to weather conditions and can change due to circumstances outside of council's control.

Contractors carry out this work on behalf of council.

Detours may be in place to assist with traffic flow during these times and every attempt will be made to minimise disruptions. Your patience while this important work is carried out is appreciated.

Please slow down and follow traffic directions near all road works, for your safety and that of the people working on the roads.

Day work generally starts at 7 am and finishes at 5 pm.

Suburb    Street Start Date Notifications Duration
Division 2   Buccleugh Street, Crees Parade, Roderick Street and Seaview Terrace, Moffatt Beach 27 October Road Reseal 4 days
Division 2   Nothling Street, Grogor Street and Seaview Terrace Moffatt Beach 9 November Road Reseal 1 week
Division 2   Wellington Parade, Shelly Beach 15 November Road Reseal 2 days
Division 2   Mahia Terrace (service road) Kings Beach 25 October Kerb & Channel replacement 1 week
Division 2   Alfred Street, Shelley Beach 25 October Kerb & Channel replacement 2 weeks
Division 5   Lawrence Place, Maleny 22 October Road Reseal
2 days
Division 6   Grandville Court, Buderim 21 September Rehabilitation 6 weeks
Division 7   Various roads 15 October Maintenance road surface line marking 8 weeks
Division 7   Page Street and Pike Street, Kunda Park 13 September Kerb and Channel Replacement 4 weeks
Division 9   Verrierdale Road, Verrierdale 13 September Rehabilitation 8 weeks
Division 9
Duke Road, Doonan 20 October Kerb and Channel replacement 1 week

Road Spray Seal
 










































Night work occurs between 6 pm and 5 am.

Suburb​

Street 

Start date 

Notifications Duration
Division 2 Buccleugh Street, Crees Parade, Roderick Street, Seaview Terrace Moffat Beach 19 October Road Reseal 2 weeks
Division 5 Willow Lane Car Park, Maleny 8 November Reseal 2 days
Division 7 Page Street and Pike Street, Kunda Park 1 November Road reseal 2 weeks
Division 7 Various Roads 15 October Maintenance road surface line marking  8 weeks

























Traffic management

Local residents will be able to access their properties during working hours and traffic management measures will be in place for the safety of pedestrians and motorists.

Vehicle movement in the streets will be restricted when work starts and every attempt to minimise disruptions will be made. 

It is recommended to plan ahead and allow more time for your travel during work periods. 

Your cooperation and patience is appreciated while work is underway.

More information

If you would like more information on the program please contact council's customer service centre