Schedule of work
  • Last updated:
  • 15 Oct 2020

The schedule of work is subject to weather conditions and can change due to circumstances outside of council's control.

Contractors carry out this work on behalf of council.

Detours may be in place to assist with traffic flow during these times and every attempt will be made to minimise disruptions. Your patience while this important work is carried out is appreciated.

Please slow down and follow traffic directions near all road works, for your safety and that of the people working on the roads.

Day work generally starts at 7 am and finishes at 5 pm.

Suburb  Street Start Date Notifications Duration
Bli Bli Aquila Court
12 October
Road Rehabilitation
8 weeks
Bli Bli
Atkinson Road
12 October
Road Reseal
8 weeks
Bli Bli
Cygnus Place
12 October
Road Reseal
8 weeks
Bli Bli
Francis Road
12 October
Road Reseal
8 weeks
Bli Bli
Inspiration Court
12 October
Road Reseal
8 weeks
Coolum Beach
Edith Place
15 October
Road Reseal
10 days
Coolum Beach
Katie Close
15 October
Road Reseal
10 days
Coolum Beach
Bagend Close
7 October
Road Rehabilitation
17 days
Division 2 Various Roads 6 October
Maintenance road surface line marking 4 weeks
Division 3 Various Roads 19 October Maintenance road surface line marking
5 weeks
Golden Beach
Booker Parade
21 September
Road Reseal
6 weeks
Golden Beach
Michael Street
21 September
Road Reseal
6 weeks
Maroochydore
Birkai Street
23 October Road Reseal
8 days
Maroochydore
Centenary Crescent
23 October Road Reseal
8 days
Nambour Reilly Road
12 October Kerb & Channel 
9 days
Pelican Waters
Sir Joseph Banks Drive
16 October Road Reseal 10 days 
Woombye Dinmore Street
16 October Road Reseal
15 days
Woombye
Wakefield Street
16 October
Road Reseal
15 days

Road Spray Seal
 




















Night work occurs between 6 pm and 5 am.

Suburb​

Street 

Start date 

Notifications Duration
Division 2
Various roads
6 October Maintenance road surface line marking
4 weeks
Division 3
Various roads
19 October Maintenance road surface line marking
5 weeks














Traffic management

Local residents will be able to access their properties during working hours and traffic management measures will be in place for the safety of pedestrians and motorists.

Vehicle movement in the streets will be restricted when work starts and every attempt to minimise disruptions will be made. 

It is recommended to plan ahead and allow more time for your travel during work periods. 

Your cooperation and patience is appreciated while work is underway.

More information

If you would like more information on the program please contact council's customer service centre