Other work in progress
  • Last updated:
  • 22 Oct 2021

Current capital improvement projects: [5872KB]Capital Works Delivery

Other minor capital projects may also be underway. Some projects may take a bit longer than anticipated to complete due to extended periods of rain, or contractors availability. You can also follow the progress of council's major regional projects.

Works listed alphabetically by suburb

Displaying 21 results

  • Battery Hill, Careen Street and Ikara Street Pathway Construction
    • Start date:
      25 Oct 2021
    • Duration:
      2 weeks
    • Related document:

    Works will begin soon on the installation of a new 1.8-metre-wide pathway along Careen Street from Nicklin Way to Ikara Street, Battery Hill. The pathway will continue south along Ikara Street to Coraki Street connecting with existing pathway.

    Work is scheduled to start the week beginning Monday 25 October 2021 and is expected to be completed within 2 weeks.

     Your patience during construction is appreciated.

  • Bli Bli Oyster Bank Road Bli Bli Oyster Bank Road Gravel Road Upgrade
    • Start date:
      05 Oct 2021
    • Duration:
      Four months
    • Related document:

    The gravel section on Oyster Bank Road, Bli Bli will be upgraded to a 6-metre-wide bitumen road with localised narrowing to 3.5 metres. Council is planning to start construction in October 2021.

  • Bridges Lees Road Bridges Lees Road Sealing and Improvements
    • Start date:
      23 Aug 2021
    • Duration:
      Four months (weather and site conditions permitting)
    • Related document:

    Sunshine Coast Council will soon begin construction on the sealing of Lees Road, Bridges.  Sections of the existing road will be upgraded to a four-metre-wide sealed section with 0.5 to 1 metre wide shoulders.

    Council will begin construction with sections one, three and four,  Subject to available funding Council will proceed to construct section two. However, if the balance of funding is not sufficient, works will be planned at a future time.

  • Buddina, Alan Walker Park Shelter and BBQ Renewal
    • Start date:
      05 Oct 2021
    • Duration:
      6 weeks
    • Related document:

    This park will be upgraded commencing Tuesday 5 October 2021. Works are scheduled to be completed in 6 weeks.

    The immediate area of the construction works will be fenced. Footpaths around the work site will remain open during construction.

     Your patience and cooperation during construction is appreciated.

  • Buderim, Stringybark Road and Gleneagle Court Intersection Roundabout Upgrade
    • Start date:
      17 Sep 2021
    • Duration:
      18 weeks
    • Related document:

    The intersection and roundabout at the Stringybark Road and Gleneagle Court, Buderim will see upgrades to allow for better access into Matthew Flinders Anglican College and improve traffic flow.

    The works will be staged and commence 20 September with the 2nd stage commencing 2 December 2021.

  • Coolum Beach Cinnamon Avenue Coolum Beach Cinnamon Avenue Stormwater Culvert Replacement
    • Start date:
      25 Oct 2021
    • Duration:
      18 weeks weather and site conditions permitting
    • Related document:

    The six-cell box culvert under Cinnamon Avenue, Coolum Beach has reached the end of its serviceable life.

    Following completion of the early weed and vegetation management works in June this year, works to replace the major culverts are now due to commence Monday 25 October 2021

  • Eumundi Memorial Drive Eumundi Memorial Drive Pathway Construction
    • Start date:
      18 Oct 2021
    • Duration:
      Two weeks, weather and site conditions permitting
    • Related document:

    Works will begin soon on the installation of a new 1.8 metre-wide pathway along Memorial Drive from Low Street to 39 Memorial Drive in Eumundi.

    The new pathway will provide both improved connectivity and pedestrian safety for bus users and the community.

  • Glenview, Glenview Road Glenview, Glenview Road Widening and Resealing
    • Start date:
      01 Feb 2021
    • Duration:
      Seven months
    • Related document:

    Council has received funding from the Australian Government’s Local Roads and Community Infrastructure Program (LRCI Program) to continue the upgrade of Glenview Road, Glenview. The remaining 1km length of narrow bitumen from Old Gympie Road will be widened and sealed.

    Works will include increasing the road sealed width from 5.5m to 7m, linemarking, tree clearing, drainage improvements and road signage.  As part of Council’s commitment to environmental sustainability, offset planting will be undertaken to compensate tree removal.  

    Council is planning to start construction in February 2021. Works are expected to finish by late September 2021 (weather and site conditions permitting).

    Construction Notification - Glenview Road Upgrade Stage 3, construction underway[676KB]

  • Golden Beach - Landsborough Parade Bridge Concrete Coating
    • Start date:
      11 Oct 2021
    • Duration:
      8 weeks
    • Related document:

    Works are in progress to improve the durability and appearance of the bridge on Landsborough Parade at Golden Beach.

    The aim is to treat any potential corrosion to ensure longevity and safety, to recoat the concrete structure to extend its working life and to clean the concrete bridge surfaces.

    Council thanks you for your patience and cooperation.

  • Golden Beach Anning Avenue Golden Beach Anning Avenue Pathway construction (Verdon St to Barnett St)
    • Start date:
      05 Oct 2021
    • Duration:
      Two weeks
    • Related document:

    Works will begin soon on the installation of a new 1.8-metre-wide pathway along Anning Avenue to Barnett Street, Golden Beach.  The pathway will extend from the childcare at Verdon Street and connect the lane to the Esplanade, opposite Barnett Street.