- Last updated:
- 13 Feb 2021
The upgrade of McGilchrist Road, Eudlo from a gravel road to a sealed road provides formalised road lanes, and increased visibility for motorists. This upgrade will also help to reduce dust and maintenance costs.
Project scope
McGilchrist Road will be sealed between Ilkley Road and Dales Road. Work will be undertaken in two stages, with the first stage from Ilkley Road to Culgoa Road and the second stage immediately south of the Dales Road intersection.
Project update
The majority of Stage 1 (Ilkley Road to Banyan Road) was completed in March 2019. The remaining section of works is the upgrade of the Eudlo Creek crossing and this is scheduled to be completed along with Stage 2 works in August 2020.
Stage 2 will see the remaining gravel section of road, south of Dales Road intersection, be upgraded to an 8m wide bitumen sealed road. Works have commenced and will be completed by the end of this calendar year (weather permitting).
Community updates
- Construction Notification March H3356 McGilchrist Road Upgrade[375KB]
- Project News McGilchrist Road Upgrade[293KB]
- Project News - April 2018[395KB]
Where to from here
Stage 1 culvert work is scheduled to start August 2020 and is expected to be completed within 4 months (weather permitting)
Overview
This project will make McGilchrist Road smoother, safer and easier for motorists to drive on. Work includes:
- widening and sealing the road to 8m, which will include a 3m traffic lane and 1m shoulder in each direction
- improving drainage structures including pipes and culverts
- realigning table drains
- improving intersection layout.
Background
As part of council’s 10 year Capital Works Program, a number of gravel roads are identified on a priority basis for sealing each financial year.
Funding for the sealing of McGilchrist Road, Eudlo has been approved for the 2019/20 and 2020/21 financial years.