Coolum Beach Cinnamon Ave Stormwater Culvert Replacement
  • Last updated:
  • 09 May 2022

Council is committed to the continual renewal and improvement of stormwater assets across our region. The six-cell box culvert under Cinnamon Avenue, Coolum Beach has reached the end of its serviceable life and is due for replacement.

Project scope

Following the completion of the early weed and vegetation management works conducted in June 2021. The drainage structure underneath Cinnamon Avenue is due to be replaced for safe and effective drainage in the area.

Project update

Construction started Tuesday, 2 November, 2021 and was set for completion end of March 2022, weather and site conditions permitting.

Due to circumstances outside of Council’s control, including inclement weather, and the unanticipated Unitywater works on a rising sewer main, the construction has been extended into May 2022. The Project team would like to express appreciation to all residents and road users for their continued patience with this prolonged construction and would like to apologise for any inconvenience the works may have caused.  Notifications distributed to the community during construction are outlined below: 

Overview

Construction will involve the replacement of the six-cell 1800 x 1200 reinforced box culverts as well as upstream open drain improvement works.

Traffic conditions between Fourwinds Avenue and Spindrift Avenue will change during the construction as detailed below:

  • Tuesday, 2 November – Tuesday, 16 November 2021: Through traffic available under controlled conditions
  • Wednesday, 17 November – Thursday, 12 May 2022: Road Closure will be in place
  • Friday, 13 May 2022: Through traffic available under controlled conditions

Traffic management measures will be in place throughout construction to ensure the safety of all road users. 

Pedestrian access will be available  via a temporary pathway around the site, for the full duration of works.

Signs will be in place, well in advance of the closure zone, to notify drivers of the changed traffic conditions. Council encourages all road users to plan and seek alternate routes where possible during this period.

Please refer to the variable message signage boards in place on both approaches to the site for the latest traffic control updates.

Contacts

If you require additional information regarding this project, or wish to speak to a member of the project team, please call (07) 5475 7272 or email us - reference P-H8974.